Phases, crews, and dependencies on one board. When the inspector pushes to Thursday, you find out what that does to drywall, to the painter, and to the draw — before you call anybody.
You already told BLT what the job costs and who is on it. That is most of a schedule. It drafts phase order, durations from the dollars and the crew size, and the obvious dependencies — then hands it to you as a starting point to argue with.

The rough-in inspection got pushed two days. Here is what the board did about it, and what it asked you to decide.
Schedules do not slip because someone was slow. They slip for three reasons, and the board treats all three as first-class facts rather than notes in a margin.
Mark a weather day and the phases that cannot run in rain move; the ones that can, don’t. Interior trim keeps its dates while the pour and the roof deck shift together, and the count of weather days used sits against the contingency you allowed for them.
An inspection is a hold, not a task. Nothing downstream of it can start until it clears, and a failed inspection reopens the phase with the photo that failed it attached. The waiting time is visible as waiting rather than disguised as work.
The switchgear is sixteen weeks and the windows are nine. Long-lead items are scheduled backwards from the day they are needed on site, with the order-by date on the board as its own item. Miss it and the board says so while there is still time to act.
Most builders keep a schedule in one place and a budget in another, and the two agree for about a week. Here they are the same phases, so a date change is a cash change and everybody can see both.
Let BLT draft the first schedule off your budget, then argue with it. One project free, no card.